Ipswich School Building Committee - November 12, 2026

ICAM Recording

Citizens Queries – M. Dougherty

Gary Champion (3 Palomino Way) objected that a draft Owner's Project Manager (OPM) Request for Services posted online lists "Town Hall" among the sites to review. He argued it should say "Green Street Playfields" because converting Town Hall into a school would be extremely complex and unlikely to succeed. The Chairman said Bialek Park was removed in the final version and that listing 25 Green Street reflects reuse of data from the failed 2018 project, not a specific proposal.

Update from OPM Negotiation Working Group – J. Fay

The working group of Jamie Fay, Brendan Sweeney and Tom Markham reported that it had reached a negotiated agreement with the top-ranked OPM firm, LiRo-Hill. The committee took no vote on the agreement. The OPM contract totals $412,632 for LiRo-Hill and two subconsultants, a cost estimator and Capital Strategic Solutions for community outreach. The group cut about $50,000 from LiRo-Hill's initial price by removing mechanical, electrical and plumbing (MEP) and sustainability roles that duplicate the future architect's team.

The main concern was cost: the estimated total for this phase is $1,935,000 against $2,090,000 in available funds. The architect's fee remains the largest unknown.

Review OPM & MSBA Timeline – T. Markham

This item was discussion only, with no vote. The steps ahead are:
- Submission to the Massachusetts School Building Authority (MSBA), delayed by a Microsoft Outlook outage and expected November 13.
- About two weeks of possible MSBA revision requests.
- A remote MSBA OPM Review Panel meeting on December 7.
- If approved, a contract effective January 1, 2027.

Once the contract is in effect, the first priorities are developing the education plan, beginning community engagement, and starting procurement of an architect.

Update on Linebrook Road Private Property – M. Dougherty

Michael Doherty and Jamie Fay concluded that the roughly 15-acre parcel offered by its owners is unsuitable for an elementary school. The land has uneven terrain, wet low areas and an active brook, and it would not be adequate even combined with the adjacent Wedgton property. The Town Manager has asked Planning and Open Space to check the findings against state Department of Environmental Protection (DEP) wetland mapping before the owners are formally notified. Fay suggested Dr. Blake consider whether the portion of the parcel next to the high school fields could be useful for athletics.

Approval of Meeting Minutes – M. Dougherty

The committee approved the minutes of October 26, 27 and 29, 2026, with one abstention. The October 29 minutes were amended to list Brendan Sweeney instead of Tom Younger. One member said they had not been able to review the minutes because of the Outlook outage.

Future Meeting Dates – M. Dougherty

The committee confirmed a standing monthly meeting on the second Thursday at 6:00 p.m. in Meeting Room A, with no objections. Upcoming dates are December 10 (may be canceled if there is not enough business) and January 14, 2027. The January meeting is planned as the kickoff with the OPM firm.

Adjourn

The committee voted unanimously to adjourn.

Key Decisions

  • Minutes of October 26, 27 and 29, 2026: Approved as amended.
    • Amendment: the October 29 minutes now list Brendan Sweeney in place of Tom Younger.
    • Motion by "Rob" and second by Jamie Fay, as stated by the Chair.
    • One abstention (Mr. Carroll); otherwise in favor.
  • OPM contract negotiation: Agreement reached with LiRo-Hill by the working group. The committee did not vote on it.
    • OPM contract: $412,632 for LiRo-Hill plus two subconsultants. LiRo-Hill's direct share was stated inconsistently as $368,000 and $318,000.
    • Negotiated down about $50,000 from initial proposal.
    • Estimated total cost for this phase: $1,935,000, including about $50,000 in contingency.
    • Available funds: $2,090,000, made up of the $2M Town Meeting appropriation plus $90K in state funds secured via Senator Tarr.
    • Resulting buffer: about $155,000, or about $200,000 counting the contingency.
    • Final approval rests with the MSBA OPM Review Panel on December 7. If approved, the contract takes effect January 1, 2027.
  • Linebrook Road private parcel: Found unsuitable for an elementary school (finding only, no vote). The finding is pending GIS and wetland confirmation by town staff.
  • Meeting schedule: Confirmed as the second Thursday of each month at 6:00 p.m. in Meeting Room A. Next dates are December 10, 2026 (tentative) and January 14, 2027.
  • LiRo-Hill invitation: Chair agreed that Tom Markham may invite LiRo-Hill to the January 14 meeting.
  • Adjournment: Passed unanimously. Motion by Chris, second by Alicia.
  • December 7, 2026 — MSBA OPM Review Panel (remote, public) to consider the Lyro Hill selection
  • December 10, 2026 — School Building Committee regular meeting, 6:00 p.m., Meeting Room A (may be canceled if there is not enough business)
  • January 1, 2027 — Target effective date of the OPM contract, if MSBA approves
  • January 14, 2027 — School Building Committee meeting, planned kickoff with the OPM firm; full attendance requested
Michael S. Dougherty [5:32] Good evening, everybody. With it being 6 o'clock and a quorum of the School Building Committee present, I'd like to call to order the Thursday, November 12th School Building Committee. As always, we start our meetings with the Pledge of Allegiance. So for all those able and willing, please join me with the pledge. I pledge allegiance to the flag of the United States of America and to the republic for which it stands. One nation under God, indivisible, with liberty and justice for all. All right. Next on our agenda, citizen queries. Are there any citizens in the audience with a query? If so, please step up to the podium and introduce yourself. Welcome. Gary Champion [6:15] Thank you, Michael. Gary Champion, 3 Palomino Way, with always a brief citizen query. There is a document on the the school building committee's website. It's labeled as a draft owner's project manager RFS. So it says under 3.4 feasibility study objectives and responsibilities, item 3, limit the review and analysis of possible site locations to the 5 previously identified sites in the prior feasibility study. Namely the Doyon School campus, campus, the Winthrop School campus, Town Hall, Mile Lane fields and surrounding area, and Bielek Park. Bielek Park's been removed, I believe,